Modernization

Orsk Oil Refinery

Upgrading results

From 2012 to the beginning of 2019, investments in the upgrade of the Orsk refinery amounted to more than
USD 1'200 million
For the period from 2019 to 2023, investments in the construction of a delayed coking complex will amount to
USD 504 million
The volume of investments in the upgrade of the Orsk refinery for the period 2012 - 2023 will be about
USD
2’000 million

ForteInvest is the main partner and shareholder of Orsknefteorgsintez. The company supplies crude oil to the refinery and sells finished products to the domestic and international markets.

Since 2012, at the Orsk Refinery, with the active participation of the shareholder - ForteInvest, one of the largest production upgrade programs in Russia has been implemented. As part of a trilateral agreement with the Ministry of Energy of the Russian Federation and the regional administration, the Orsk Refinery is implementing a large-scale program for the reconstruction and upgrade of plant facilities. The main goal of the upgrade initiative is to produce high-quality products at the European level in order to maximize environmental protection.

The enterprise implements all projects in accordance with the planned schedules and existing standards for the production of petroleum products. It is noteworthy that the construction of new facilities goes on without interrupting the work of the plant - production is carried out in a planned mode, the region receives oil products in accordance with the need for them, there is no shortage of oil products.

At present, the refinery has implemented Stage 1 of the Orsk Refinery Development Program for the period 2012–2019 and includes 4 launch complexes. The development program is designed in such a way that the implementation of each start-up complex is aimed at improving the quality of products, increasing the depth of processing and increasing the yield of light oil products. The total investment for this period amounted to 64 billion rubles including VAT of $1.2 billion.




Upgrade results 2011-2024

48,8% 2012
72% 2020
84% 2024
Light petroleum products yield
59,5% 2012
88% 2020
98,6% 2024
Refining depth

Stage 2

Stage 1

2024 Class 5 motor fuels
2020 Class 5 motor fuels
2012 Class 2 motor fuels
Products
1

Development program

DEVELOPED BY CJSC “NEFTEСHIMPROEKT” IN MAY 2021

2012

Program
Stage 1

2019 2026

Program
Stage 2

Program stage 1

Was implemented from 2012 to 2019.
It consists of 4 start-up facilities and includes the following projects:

  • 1st START-UP COMPLEX:
  • SF 1. Reconstruction of the LCh-24-2000 diesel fuel hydrotreating unit (2 stages)

    Project goals:
    Hydrotreating the diesel fraction to the requirements of class 5;
    Bringing the unit to the current standards;
    Hydrotreating the gasoline fraction from the tar visbreaking unit.


    Start of reconstruction: April 2013
    End of reconstruction: September 2014

  • SF-1. Construction of a hydrogen production unit

    Project goals:
    Providing hydrogen (99.9% purity) to the LCh-24-2000 diesel fuel hydrotreating unit.

    Start of construction: January 2014
    End of construction: September 2016

  • 2nd START-UP FACILITY:
  • SF-2. Reconstruction of the 22-4 rectification unit

    Project goals:
    Providing the isomerization unit with high-quality feedstock;
    Reduction of benzene-forming hydrocarbons in feedstock of reforming units, decrease in benzene content in produced motor gasolines;
    Bringing the unit to the current standards;

    Start of reconstruction: June 2013
    End of reconstruction: November 2014

  • SC-2. Isomerization unit construction

    Project goals:
    Production of commercial isomerate of С5, С6 hydrocarbons for the organization of the production of class 5 motor gasoline at the enterprise

    Licensor: ОNPP Neftekhim.
    Start of construction: November 2012
    End of construction: December 2014

  • 3rd START-UP COMPLEX:
  • SF-3. Construction of a tar visbreaking unit

    Project goals:
    Reduction of production of boiler fuel/heating oil at the enterprise
    Freeing up the vacuum gasoil resource for further processing at the hydrocracking unit.

    Licensor: Amec Foster Wheeler
    Start of construction: April 2014
    End of construction: September 2015

  • 4th START-UP FACILITY:
  • Sf-4. Construction of a hydrocracking unit with a hydrogen production section

    Project goals:
    Increase in the output of light petroleum products at the enterprise through processing of vacuum gasoil.

    Licensor and Catalyst Supplier: Shell Global Solutions
    Start of construction: October 2015
    End of construction: October 2018

  • SF-4. Construction of an elemental sulfur production unit

    Project goals:
    Processing of sulfur-containing emissions from the hydrocracking unit and other facilities of the enterprise.
    Obtaining pelletized sulphur.

    Start of construction: October 2015
    End of construction: September 2018

  • SF-4. Construction of the fuel oil vacuum distillation unit

    Project goals:
    Increase in vacuum gasoil recovery as feedstock of the hydrocracking unit and improvement of tar quality.

    Start of construction: May 2017
    End of construction: June 2019

  • SF-4. Technical re-equipment of the vacuum column K-6 of the CDU/VDU unit

    Project goals:
    Increase in vacuum gasoil recovery and quality assurance in accordance with the requirements of the hydrocracking unit.
    Improving the quality of vacuum diesel fuel.
    Improvement of the tar quality.

Program stage 2

Currently, the enterprise is implementing the second stage of development, which includes construction of new and reconstruction of existing facilities.

An Investment Agreement was signed in March of this year with the Ministry of Energy of the Russian Federation for the creation of new deep processing facilities in respect of PJSC "Orknefteorgsintez".

Under this Agreement, the following facilities will be implemented at the Orsk Refinery:


- Construction of the gasoline and diesel fraction hydrotreating unit;

- Construction of the delayed coking unit (1.2 million tons of tar per year) with off-plot facilities;

- Reconstruction of the hydrocracking complex and a gasoline isomerization unit with a feedstock preparation unit;

2012

48,8%

Light petroleum
products
yield
2026

84%

2012

59,5%

Refining depth
2023

98,6%

The timeline of the Orsk Refinery modernization

from 2011 to 2022

  • 2011

    Establishment of CJSC "ForteInvest", examination of technical equipment of the refinery, development of preliminary documentation on its modernization

    May 2012

    Approval of the long-term Orsk Refinery Modernization Program and commencement of work

    November 2012

    Start of the isomerization complex construction

    December 2012

    Completion of the catalytic reformer unit reconstruction

    December 2012

    Launch of a light petroleum products on-spot loading rack

    Result

    Improvement of safety and environmental performance when loading petroleum products.

    May 2013

    Start of the LCh-24-2000 diesel fuel hydrotreating unit reconstruction

    June 2013

    Start of the 22-4 unit reconstruction



Currently, the refinery has reconstructed the existing facilities, and more than 15 large modern facilities have been constructed. Among the most significant of the facilities are: petroleum products on-spot loading rack, light naphtha fractions isomerization unit, tar visbreaking unit, hydrogen production unit, sulphur production unit with a pelletization unit, hydrocracking complex.

The modernization program for the period 2012-2023 will allow the enterprise to become one of the most reputable and dynamically developing in our country.


As a result of modernization, the refining depth at the Orsk refinery increased
from 59% to 98%



the yield of light petroleum products amounted to about

84% against 49% in 2012